Hwy 20 and Hamby/Ward Roundabout Project (ODOT)

Updates on the Hwy 20 Hamby/Ward Roundabout:

Hwy20 Hamby/Ward Roundabout Update -3/21/22

By Mike Whitter | March 21, 2022

Construction of the roundabout is underway. The contractor has closed Hamby Road at U.S. 20 until April 8. Ward Road at U.S. 20 will be closed starting Tuesday morning on March 22 through April 26. Please use alternate routes during these closures; detour routes will be posted on site.

Hwy20 Hamby/Ward Roundabout Update -2/14/22

By Mike Whitter | February 14, 2022

US 20: Ward-Hamby Road Intersection Project (Bend Area) – Starting on February 15, a road closure on Hamby Road will be occurring as part of the ODOT US 20 Ward/Hamby roundabout project. Hamby Road will be closed to through-traffic between US 20 and Neff Road from approximately February 15 through March 1. A designated detour route is in place via US 20, Erickson Road and Neff Road.

Hwy20 Hamby/Ward Roundabout Update -1/03/22

By Mike Whitter | January 4, 2022

Weekly Construction Update

U.S. 20: Ward/Hamby Rd. Intersection Project (MP3.26-MP3.86)
 
Jan.03-07, 2022
 
ODOT will construct a single-lane roundabout at the intersection of U.S. 20 and Ward/Hamby roads. No project work this week due to inclement weather.
 
Ward/Hamby roundabout
Construction of the Ward/Hamby roundabout on U.S. 20 east of Bend is now under way, though earthwork will likely begin in the spring.

Sign up for Road Work News!

Interested in getting the latest news on traffic alterations around town?