Neff and Purcell Intersection Project

Updates on the Neff and Purcell Intersection Project:

Transportation – Neff-Purcell Construction Update 7/21/2023

By Mike Whitter | July 24, 2023

CONSTRUCTION UPDATE – July 24–31

Purcell Extension

  • Pre-paving preparation work continues on the new roadway section of the Purcell Boulevard extension. Paving of this section is targeted for late July. Purcell Boulevard will remain closed until the completion of the modernization.
  • Concrete curb and sidewalk through the extension portion has been completed.
  • The full closure of the modernization portion of Purcell Boulevard continues as crews continue to work on water, sewer, and stormwater infrastructure. Impacted properties will receive notice if their water service is expected to be impacted.
  • Demolition of existing right of way surfaces is ongoing.
  • Striping of bike lanes along Purcell Blvd from Butler Market Road to Robinson Street is scheduled to occur the first week of August. During striping and after striping is complete, there will be No parking allowed along Purcell Boulevard within this stretch of roadway.

Neff and Purcell Intersection

  • The franchise utilities, such as gas, power, cable, etc., are progressing towards completion of relocating facilities to their ideal locations and depths.
  • Replacement and installation of the sewer pipelines and manholes continues throughout all segments of the intersection.
  • Installation of the new stormwater systems is ongoing.
  • Excavation for the storm water system at the intersection of Cliff Drive and Neff Road continues.
  • Patch paving of Cliff Drive near Neff Road will be performed on Wednesday, July 26.

RESOURCES

Commute Options

  • Commute Options is here to help you with transportation options during construction. Join the Neff/Purcell Improvement Project network on Get There Connect to match up in a carpool, explore your transit, biking, walking options, help reduce traffic and more! Sign up today and learn more about your chance to win a $50 gift card! Visit Commute Options for more information.

Project Communications

  • The City is committed to keeping neighbors, businesses and the community informed throughout the project through public informational meetings, mailings, emails and the project website. For more information, contact the project team at neffpurcell@bendoregon.gov.
  • Please contact us if you need any additional materials that would be helpful to spread the word to your patients, clients, customers and delivery personnel regarding detouring and closures.
  • Share the website information where others can also sign up for updates: bendoregon.gov/neff-purcell

ROAD CLOSURES AND DETOURS 

Neff and Purcell Intersection Detour Routes

  • Eastbound (south option) – go south on Eighth Street, east on Greenwood Avenue, north on 27th Street
  • Eastbound (north option) – go north on Eighth Street, east on Butler Market Road and south on 27th Street
  • Westbound (south option) – go south on 27th Street, west on Greenwood Avenue, north on Eighth Street
  • Westbound (north option) – go north on 27th Street, west on Butler Market Road and south on Eighth Street

Temporary Pedestrian Access Routes

Please use marked temporary pedestrian detours. Please be aware these temporary pedestrian access routes will change as needed during different phases of work.

Interactive Traffic Impacts Map

You may also monitor current and upcoming detours and closures at bendoregon.gov/traffic.

QUESTIONS AND COMMENTS? 

This project is partly funded by the voter-approved 2020 Transportation General Obligation (GO) Bond. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.

Transportation – Neff-Purcell Construction Update 6/30/2023

By Mike Whitter | June 30, 2023
With a number of construction improvements underway throughout the community, we would like to express our appreciation of the public’s patience as roadway and utility infrastructure improvements continue.

Have a safe and happy Fourth of July!

PROJECT UPDATE

deep sewer trench work with various utility lines crossings
     (Photo above: Sewer structure and main line work – Neff and Purcell intersection)

CONSTRUCTION – July 3 – July 7

In observance of Independence Day on Tuesday, July 4th, there will be limited personnel on site.

Purcell Extension

Processing of the excavated and hammered material adjacent to Courtney Drive is completed.

The Full closure of Purcell continues as crews begin water and sewer service line work. Impacted properties will receive notice if their water service is expected to be impacted.

Demolition of existing right of way surfaces continues.

Neff and Purcell Intersection

The franchise utilities such as gas, power, cable, etc. are progressing towards completion of relocating facilities to their ideal locations and depths, the City’s contractor is able to begin the planned improvements of the Neff and Purcell intersection.

Replacement of the sewer mainlines and structures continues throughout the intersection.

RESOURCES

Commute Options

  • Commute Options is here to help you with transportation options during construction. Join the Neff/Purcell Improvement Project network on Get There Connect to match up in a carpool, explore your transit, biking, walking options, help reduce traffic and more! Sign up today and learn more about your chance to win a $50 gift card! Visit Commute Options for more information.

Project Communications

  • The City is committed to keeping neighbors, businesses and the community informed throughout the project through public informational meetings, mailings, emails and the project website. For more information, contact the project team at neffpurcell@bendoregon.gov.
  • Please contact us if you need any additional materials that would be helpful to spread the word to your patients, clients, customers and delivery personnel regarding detouring and closures.
  • Share the website information where others can also sign up for updates: bendoregon.gov/neff-purcell

ROAD CLOSURES AND DETOURS 

Neff and Purcell Intersection Detour Routes

  • Eastbound (south option) – go south on Eighth Street, east on Greenwood Avenue, north on 27th Street
  • Eastbound (north option) – go north on Eighth Street, east on Butler Market Road and south on 27th Street
  • Westbound (south option) – go south on 27th Street, west on Greenwood Avenue, north on Eighth Street
  • Westbound (north option) – go north on 27th Street, west on Butler Market Road and south on Eighth Street

Temporary Pedestrian Access Routes

Please use marked temporary pedestrian detours. Please be aware these temporary pedestrian access routes will change as needed during different phases of work.

Interactive Traffic Impacts Map

You may also monitor current and upcoming detours and closures at bendoregon.gov/traffic.

QUESTIONS AND COMMENTS? 

This project is partly funded by the voter-approved 2020 Transportation General Obligation (GO) Bond. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.

Transportation – Neff-Purcell Construction Update 6/16/2023

By Mike Whitter | June 17, 2023

SAFETY FIRST

Tips for Pedestrian and Cyclist Safety in Road Work Construction Zones

If you need to pass through a construction site on foot, here are some safety tips that you can utilize to reduce your risk of accidents and injuries:

  • Keep your eye out for posted warning signs. Keep your distance from anything that could pose a risk to your safety; make sure to look for temporary barriers and signs that let you know where to go.
  • Watch your step. Always glance down as you walk so that you avoid any potential slips.
  • Make sure equipment operators can see you. As you pass a heavy piece of machinery, make sure that the operator can see you by making eye contact before continuing on.
  • Get through quickly. It’s natural for your mind to wander with curiosity while walking through a construction zone, but it’s important that you focus on being cautious, avoid cutting corners, and get through the site quickly and safely.
  • Walk your bike.

PROJECT UPDATE

Sidewalks and curbs have been installed along the Purcell Boulevard extension.

Purcell extension construction near the intersection of purcell and courtney

Construction – June 19–23

Purcell Extension

A full closure of Purcell Boulevard from Full Moon Drive through Holliday Avenue will begin mid-week as demolition work begins. The intersection of Full Mood Drive and Purcell Boulevard will remain OPEN to traffic. The intersection of Holliday Avenue and Purcell Boulevard will be CLOSED to traffic – use posted detour.

Crews will begin installing stormwater structures.

Processing of the excavated and hammered material continues near Courtney Drive. The crushed rock will be repurposed for pipeline backfill and to change the grade of Neff Road through the intersection.

Neff and Purcell Intersection

Rock hammering and excavation continues for stormwater infrastructure improvements. Installation of sewer structures and pipe continues throughout the intersection.

The franchise utilities such as gas, power, cable, etc. are progressing towards completion of relocating facilities to their ideal locations and depths, the City’s contractor is able to begin the planned improvements of the Neff and Purcell intersection.

RESOURCES

Commute Options

  • Commute Options is here to help you with transportation options during construction. Join the Neff/Purcell Improvement Project network on Get There Connect to match up in a carpool, explore your transit, biking, walking options, help reduce traffic and more! Sign up today and learn more about your chance to win a $50 gift card! Visit Commute Options for more information.

Project Communications

  • The City is committed to keeping neighbors, businesses and the community informed throughout the project through public informational meetings, mailings, emails and the project website. For more information, contact the project team at neffpurcell@bendoregon.gov.
  • Please contact us if you need any additional materials that would be helpful to spread the word to your patients, clients, customers and delivery personnel regarding detouring and closures.
  • Share the website information where others can also sign up for updates: bendoregon.gov/neff-purcel

ROAD CLOSURES AND DETOURS 

Neff and Purcell Intersection Detour Routes

  • Eastbound (south option) – go south on 8th Street, east on Greenwood Avenue, north on 27th Street
  • Eastbound (north option) – go north on 8th Street, east on Butler Market Road and south on 27th Street
  • Westbound (south option) – go south on 27th Street, west on Greenwood Avenue, north on 8th Street
  • Westbound (north option) – go north on 27th Street, west on Butler Market Road and south on 8th Street

Temporary Pedestrian Access Routes

Please use marked temporary pedestrian detours. Please be aware these temporary pedestrian access routes will change as needed during different phases of work.

Interactive Traffic Impacts Map

You may also monitor current and upcoming detours and closures at bendoregon.gov/traffic.

QUESTIONS AND COMMENTS? 

This project is partly funded by the voter-approved 2020 Transportation General Obligation (GO) Bond. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.

Sign up for Road Work News!

Interested in getting the latest news on traffic alterations around town?